Work Code Number : 025-09-M-J-U-B-FO-001
Name of the Project : Gopalapura slum construction of 9 no.s.TT Sheds for Gopalapura slum ward No.25.
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 505000
Workcode Approval Date : 00-00-0000 Approved Cost : 505000
Work Order Date : 27-06-2009 Expenditure Incurred : 550000
Client Name : Approved Cost in Percentage : 0
Location Details
District : Constituency : Gandhi Nagar
Zone : Head Office Department Type :
Division : Sub Division :
Ward Name : Ward No :
Locality : Postal Code :
Area : Gopalpura,Magadi Road.
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2006-07
Budget Category(Head of Account) : JNNURM
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : SE(BSUP)/AS/05/08-09  00-00-0000
Technical Sanction No and Date : SE(BSUP)/TS/05/08-09  00-00-0000
Technical Notification No and Date : Phc/Contracts/Bng(u)/BBMP-SLUM work/TND/08-0-/390  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E(BSUP)-2
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : A.R.Narayana Reddy
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Sidaram
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : R.G. Hegde
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 4 (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :03-06-2009
Commencement Date : 00-00-0000 Probable Date of completion :04-07-2009
Scheduled date of completin as per contract : 04-07-2009 Actual Date of Completion : 04-07-2009
Work Status : Completed Spill Over / Programme of Work and Year : Spill Over  
Percentage of Physical Progress : 0 Remarks : Work Completed