logo
Workcode & Project Details
Work Code Number : 011-11-000022
Name of the Project : Improvements of Roads , Culvert, Covering and Construction of Concrete, Molded Drains at Vinayaka nagara behind Govt. School, area
Short Name of Project :Culvert, Covering and Construction of Concrete, Molded Drains at Vinayaka nagara
Project Code : Package Code : 0
Date of Issue of Workcode : 16-12-2010 Estimated Cost : 1000000
Workcode Approval Date : 16-12-2010 Approved Cost : 1000000
Work Order Date : 29-03-2011 Expenditure Incurred : 1031788.71
Client Name : EKADANTA CONSTRUCTIONS Approved Cost in Percentage : 4.6
Location Details
District : Constituency : Byatarayanapura
Zone : Yelahanka Department Type :
Division : Byatarayanapura Sub Division : Vidyaranyapura
Ward Name : Kuvempu Nagar Ward No : 11
Locality : Postal Code : 560 0092
Area :
Approval Details
Approved By : CE
Year of SR Adopted for Preparation of Estimate : 2010-11
Budget Category(Head of Account) : P1771
Scheme :
Amount Alloted : Budgeted
Administrative Approval No and Date : 176  29-01-2011
Technical Sanction No and Date : 176  29-01-2011
Technical Notification No and Date : 02/10-11  21-01-2011
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : Sri.P.S.Ramesh
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : EE(Byatarayanapura)
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : AEE(Vidyaranyapura)
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : AE(Kuvempu Nagar)
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Contractor Name :
Work Status Details
Agreement No. & Date : 185  29-03-2011 Site Handed Over Date :17-03-2011
Commencement Date : 17-03-2011 Probable Date of completion :29-06-2011
Scheduled date of completin as per contract : 29-06-2011 Actual Date of Completion : 26-07-2011
Work Status : Completed Spill Over / Programme of Work and Year : POW  
Percentage of Physical Progress : 100 Remarks :
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 04-05-2024 08:51:50