Work Code Number : 061-010-M-G-D-IM-003
Name of the Project : Construction of culverts in 6th Cross Kamkshipalya in Ward No.61.
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 200000
Workcode Approval Date : 00-00-0000 Approved Cost : 215000
Work Order Date : 02-11-2009 Expenditure Incurred : 215000
Client Name : Approved Cost in Percentage : 7.9
Location Details
District : Constituency : Rajaji Nagar
Zone : West Department Type :
Division : Rajaji Nagar Sub Division : Rajaji Nagar
Ward Name : Kamakshipalya Ward No : 101
Locality : Postal Code :
Area : Kamakshipalya
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : 2009-10
Budget Category(Head of Account) : P.O.W.
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : 352/09-10  00-00-0000
Technical Sanction No and Date : 352/09-10  00-00-0000
Technical Notification No and Date : EE/RNR/TEND/03/09-10  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E.(WEST)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Gurunath
Designation : Executive Engineer
User ID : 32103
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Arunkumar
Designation : AEE
User ID : 3210301
Mobile Number :
Email Id :
Ward Engineer
Name : Ramakrishna
Designation : Assistant Engineer
User ID : 321030103
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 2 (Civil) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :02-11-2009
Commencement Date : 00-00-0000 Probable Date of completion :01-02-2010
Scheduled date of completin as per contract : 01-01-2010 Actual Date of Completion : 01-01-2010
Work Status : Completed Spill Over / Programme of Work and Year : Emy grants   2008-09
Percentage of Physical Progress : 0 Remarks :