logo
Workcode & Project Details
Work Code Number : 018-09-M-G-T-B-FX-001
Name of the Project : Repairs and Providing additional fixtures to IPP Building at Kamakshipalya.
Short Name of Project :
Project Code : Package Code : 0
Date of Issue of Workcode : 00-00-0000 Estimated Cost : 100000
Workcode Approval Date : 00-00-0000 Approved Cost : 100000
Work Order Date : 27-12-2008 Expenditure Incurred : 109000
Client Name : Approved Cost in Percentage : 1.09
Location Details
District : Constituency : Rajaji Nagar
Zone : West Department Type :
Division : Rajaji Nagar Sub Division : Rajaji Nagar
Ward Name : Kamakshipalya Ward No : 101
Locality : Postal Code :
Area :
Approval Details
Approved By :
Year of SR Adopted for Preparation of Estimate : S.R 2007-2008
Budget Category(Head of Account) : Captial Works
Scheme : No Scheme
Amount Alloted :
Administrative Approval No and Date : 69/12  00-00-0000
Technical Sanction No and Date : 69/134  00-00-0000
Technical Notification No and Date : EE/ELE/TN/GL/26/2008-09  00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : C.E.(WEST)
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Sri. K. Govindaiah
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Sri. Puttalingaiah
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Sri Ramesh .D
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 4 (Electrical) Contractor Name :
Work Status Details
Agreement No. & Date :   00-00-0000 Site Handed Over Date :00-00-0000
Commencement Date : 27-12-2008 Probable Date of completion :28-01-2009
Scheduled date of completin as per contract : 28-01-2009 Actual Date of Completion : 05-02-2009
Work Status : Completed Spill Over / Programme of Work and Year : Programme of Work  
Percentage of Physical Progress : 0 Remarks : Nil
Category Details
Category : Type of Work : Sub Work :
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 05-05-2024 16:25:59