logo
Workcode & Project Details
Work Code Number : 005-12-000031
Name of the Project : Drilling of borewells and providing pump and motor to borewell at Kattigenahalli in ward no. 05, Byatarayanapura sub division.
Short Name of Project :Drilling of borewells and providing pump and motor to borewell at Kattigenahalli in ward no. 05, Byatarayanapura sub division.
Project Code : P-1 Package Code : 0
Date of Issue of Workcode : 21-04-2012 Estimated Cost : 500000
Workcode Approval Date : 24-10-2011 Approved Cost : 500000
Work Order Date : 04-01-2012 Expenditure Incurred : 550000
Client Name : KRIDL Approved Cost in Percentage : 10
Location Details
District : Constituency : Byatarayanapura
Zone : Yelahanka Department Type :
Division : Byatarayanapura Sub Division : Byatarayanapura
Ward Name : Jakkur Ward No : 5
Locality : Postal Code :
Area :
Approval Details
Approved By : EE
Year of SR Adopted for Preparation of Estimate : 2010-11
Budget Category(Head of Account) :
Scheme :
Amount Alloted : Non Budgeted
Administrative Approval No and Date : 114  24-11-2011
Technical Sanction No and Date : 115  07-12-2011
Technical Notification No and Date :   00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name : Sri.P.S.Ramesh
Designation : Chief Engineer
User ID :
Mobile Number :
Email Id :
Division Engineer
Name : Ravi (Incharge AEE)
Designation : Executive Engineer
User ID : 0
Mobile Number :
Email Id :
Sub-Division Engineer
Name : Mohan Gowda( Dasarahalli )
Designation : AEE
User ID : 0
Mobile Number :
Email Id :
Ward Engineer
Name : Ramakrishana Reddy
Designation : Assistant Engineer
User ID : 0
Mobile Number :
Email Id :
Contractor Info
Contractor Class : Class 1 A (Civil) Contractor Name : The Managing Director,
Work Status Details
Agreement No. & Date : 327  04-01-2012 Site Handed Over Date :04-01-2012
Commencement Date : 05-01-2012 Probable Date of completion :04-03-2012
Scheduled date of completin as per contract : 31-01-2012 Actual Date of Completion : 31-01-2012
Work Status : Completed Spill Over / Programme of Work and Year : NONPOW  
Percentage of Physical Progress : 100 Remarks : drilling borewells
Category Details
Category : Management and statistics Type of Work : Management and statistics Sub Work : Management and statistics
This Report has been generated from ETAMINE Global Project Management System - Indian CST. Date & Time: 09-05-2024 15:41:12