Workcode & Project Details
Work Code Number
: 011-13-000001
Name of the Project
: Drilling of providing and installing pipe line and Gatewalves in ward no. 11 Kuvempunagara areas (Ramachandrapura Kuvempunagara Varadarajanagara Vinayaka, Vinayakanagara M.S. Palya Valmikinagara Singapura Gangammagudi Muneshwara Block area surroundin
Short Name of Project
:Drilling of providing and installing pipe line and Gatewalves in ward no. 11 Kuvempunagara areas (Ramachandrapura Kuvempunagara Varadarajanagara Vinayaka, Vinayakanagara M.S. Palya Valmikinagara Singapura Gangammagudi Muneshwara Block area surroundin
Project Code
:
Package Code
: 0
Date of Issue of Workcode
: 16-10-2012
Estimated Cost
: 500000
Workcode Approval Date
: 13-07-2012
Approved Cost
: 524675
Work Order Date
: 18-09-2012
Expenditure Incurred
:
Client Name
: gopireddy
Approved Cost in Percentage
: 4.98
Location Details
District
:
Constituency
: Byatarayanapura
Zone
: Yelahanka
Department Type
:
Division
: Byatarayanapura
Sub Division
: Vidyaranyapura
Ward Name
: Kuvempu Nagar
Ward No
: 11
Locality
:
Postal Code
: 560007
Area
:
Approval Details
Approved By
: ee
Year of SR Adopted for Preparation of Estimate
: 2011-12
Budget Category(Head of Account)
: P0002
Scheme
:
Amount Alloted
: Non Budgeted
Administrative Approval No and Date
: 00-00-0000
Technical Sanction No and Date
: 00-00-0000
Technical Notification No and Date
: 00-00-0000
Uploaded Mobile Photos
Uploaded Photos
Stakeholders Details
Zone Engineer
Name
: Sri.P.S.Ramesh
Designation
: Chief Engineer
User ID
:
Mobile Number
:
Email Id
:
Division Engineer
Name
: Ravi (Incharge AEE)
Designation
: Executive Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Sub-Division Engineer
Name
: Mariyappa Reddy (Vidyaranyapura)
Designation
: AEE
User ID
: 0
Mobile Number
:
Email Id
:
Ward Engineer
Name
: Ramesh Babu
Designation
: Assistant Engineer
User ID
: 0
Mobile Number
:
Email Id
:
Contractor Info
Contractor Class
: Class 1 A (Civil)
Contractor Name
: Shankranarayana Consultants co.,
Work Status Details
Agreement No. & Date
: 146 18-09-2012
Site Handed Over Date
:19-09-2012
Commencement Date
: 23-10-2012
Probable Date of completion
:19-11-2012
Scheduled date of completin as per contract
: 18-11-2012
Actual Date of Completion
: 30-09-2012
Work Status
: Completed
Spill Over / Programme of Work and Year
: pow
Percentage of Physical Progress
: 100
Remarks
: borewells
Category Details
Category
: Management and statistics
Type of Work
: Management and statistics
Sub Work
: Management and statistics
This Report has been generated from ETAMINE Global Project Management System -
Indian CST.
Date & Time: 08-05-2024 09:04:46