Project Information
Officer incharge :
Sh. N.K.Jain
Name of the Project :
Providing and fixing G.I pipe ball valve hooper and other misc. sanatory item at trap and Skeet No.4 Providing and fixing G.I pipe ball valve hooper and other misc. sanatory item at trap and Skeet No.4
Work Code Number : CPWD-00001635
    Location
State : Delhi
Place : Dr.Karni Singh Shooting Range Tughlakabad New Delh
District : Delhi
    Finances
Administrative Sanction Amount in Rs : 149
Estimated Cost(in rupee only) : 50690
Revised Estimated Cost(In Rupees) : 0
Awarded Contract(In Rupee Only) : 52327
Payment (Value of work done till 00/00/0000) :
Bid Price of L1 Bidder(in Rupees ): 0
    Contract Details
Agreement Number : 04/AE-III/CWGD-IX/200-10
Contractor/Agency Name : M/s JMC Projects (I)Ltd
    Important Dates
Date of Start:
As Per Agreement As Per Actual
00/00/0000 12/12/2009
Date of Completion:
As Per Agreement As Per Actual
00/00/0000 00/00/0000
Administrative approval and expenditure sanction date : 00/00/0000
Estimate prepared on : 00/00/0000
Date of Revision of estimate : 00/00/0000
Agreement Date : 00/00/0000
Start Date : 12/12/2009
Date of opening bids :
As Per Agreement As Per Actual
Prequalification Bid 00/00/0000 00/00/0000
Technical Bid 00/00/0000 00/00/0000
Financial Bid 00/00/0000 00/00/0000
    Work details
Stipulated Agreement Time(in days) : 2 Weeks
Physical Progress of the work in percentage term : 1%
Financial Progress of the work in percentage term :
Tender Complaint : No
Mode of tendering :
Tenders received through e-tendering solutions : No
No of Tenders Received : 0
Justified Amount of the tender : 52772
Date of Preparation of Justified Amount : 00/00/0000
No's of bidder's disqualified in Prequalification : 0
No's of bidder's disqualified in Technical evaluation : 0
No of Financial bids opened : 2
Letter of intent Number :
Letter of intent Date 00/00/0000
Name of the Work manual adopted.
Complaint related to tendering or execution of the work received. No
Project / Work Status
Additional remarks, if any.
Reason For Project Updation
    Other Details
Number of extra item statements initiated and their amounts.
S.No. Extra Item Initiated Amount Date
1 Nil Nil
Number of substituted item statements initiated and their amounts.
S.No. Substituted Item Initiated Amount Date
1 Nil Nil
Number of reduction / deduction item statements initiated and their amounts.
4
S.No. Reduction Deduction Amount
1 Nil Nil Nil
Number of consultancy agencies appointed in connection with the work & their names.
S.No. No. of Consultancy Consultancy Name
1 Nil Nil
    Observations and Comparisons
PARAMETER OBSERVATION1 OBSERVATION2 REMARKS
No Records Found