Project Information
Officer incharge :
Sh. V.P. Singh
Name of the Project :
Re-modeling and up-gradation of Dr. Karni Singh Shooting Range Stadium under Common Wealth Games 2010 New Delhi dg. 2010-11. (SH: Procurement displaying & maintnenance of well bloomed seasonal flowering pots.)
Work Code Number : CPWD-00003276
    Location
State : Delhi
Place : KSSR
District : Delhi
    Finances
Administrative Sanction Amount in Rs : 2460
Estimated Cost(in rupee only) : 1580000
Revised Estimated Cost(In Rupees) : 0
Awarded Contract(In Rupee Only) : 1513000
Payment (Value of work done till 23/10/2010) :
Bid Price of L1 Bidder(in Rupees ): 1513000
    Contract Details
Agreement Number : 07/DDH/CWGP/2010-11
Contractor/Agency Name : M/s Bhagwat Flora Nursery
    Important Dates
Date of Start:
As Per Agreement As Per Actual
15/05/2010 15/05/2010
Date of Completion:
As Per Agreement As Per Actual
30/10/2010 23/10/2010
Administrative approval and expenditure sanction date : 01/06/2009
Estimate prepared on : 00/00/0000
Date of Revision of estimate : 00/00/0000
Agreement Date : 07/05/2010
Start Date : 15/05/2010
Date of opening bids :
As Per Agreement As Per Actual
Prequalification Bid 00/00/0000 00/00/0000
Technical Bid 00/00/0000 00/00/0000
Financial Bid 00/00/0000 16/04/2010
    Work details
Stipulated Agreement Time(in days) : 180
Physical Progress of the work in percentage term : 100%
Financial Progress of the work in percentage term :
Tender Complaint : No
Mode of tendering : OpenTender
Tenders received through e-tendering solutions : No
No of Tenders Received : 2
Justified Amount of the tender : 1880570
Date of Preparation of Justified Amount : 16/04/2010
No's of bidder's disqualified in Prequalification : 0
No's of bidder's disqualified in Technical evaluation : 0
No of Financial bids opened : 2
Letter of intent Number : 64
Letter of intent Date 07/05/2010
Name of the Work manual adopted. CPWD Works Manual
Complaint related to tendering or execution of the work received. No
Project / Work Status
Additional remarks, if any. N/A
Reason For Project Updation
    Other Details
Number of extra item statements initiated and their amounts.
S.No. Extra Item Initiated Amount Date
1 Nil Nil
Number of substituted item statements initiated and their amounts.
S.No. Substituted Item Initiated Amount Date
1 Ni Nil
Number of reduction / deduction item statements initiated and their amounts.
4
S.No. Reduction Deduction Amount
1 Nil Nil Nil
Number of consultancy agencies appointed in connection with the work & their names.
S.No. No. of Consultancy Consultancy Name
1 Nil Nil
    Observations and Comparisons
PARAMETER OBSERVATION1 OBSERVATION2 REMARKS
No Records Found